Appalachian Power Coal Plant’s Winter Failures Raise Reliability Questions
Appalachian Power's coal-burning John Amos Power Plant in Putnam County.Troy Rankin/West Virginia Public Broadcasting
Listen
Share this Article
Appalachian Power’s John Amos power plant is the biggest in West Virginia.
Data the company provided to utility regulators in Virginia show one of the plant’s three units failed on Jan. 21 and 22. This was during one of the coldest periods of the year, with record demand for electricity in the region.
The data show that 800-megawatt Unit 2 failed for 28 hours on those two days. The outage was recorded as unplanned. The unit was not scheduled for maintenance.
“A plant, like Amos, that is having these outages, is supposed to be reliable,” he said. “They’re getting millions of dollars for being a reliable plant that can deliver power when the grid needs it, and instead, they’re not paying a penalty, but the plant isn’t available either.”
Amos first went online in 1971 and supplies power to West Virginia and Virginia. Debra Pannell, a spokeswoman for Appalachian Power, said the performance of the company’s coal fleet aligns with the average performance in PJM, a 13-state regional grid that includes both states.
Pannell said Appalachian Power did not receive any penalties in PJM for the failure of Amos 2.
It turns out that Amos 2 was not needed to meet the high demand in January.
“So they got lucky,” Feaster said.
Days later, Amos 2 broke down again for more than 19 days in February.
A screenshot from Appalachian Power’s outage data submitted to the Virginia State Corporation Commission shows the John Amos plant’s Unit 2 was out for 28 hours on Jan. 21-22. Credit: Appalachian Power
Add WVPB as a preferred source on Google to see more from our team
Two people have died, and a third is listed in critical condition following a sudden chemical release Wednesday at a catalyst refinery plant near Nitro and Institute. Also, we listen to an excerpt from the latest Us & Them where host Trey Kay leads a community discussion at Marshall on the American Revolution.
The Wolf Summit Energy Project will be the first combined cycle power plant in West Virginia, producing 600-megawatts to be sold to Old Dominion Energy.