The Public Service Commission of West Virginia granted Monongahela Power Company and the Potomac Edison Company approval Tuesday to move forward with construction of a 1,200-megawatt combined-cycle natural gas plant and 70 MW of solar capacity at the Fort Martin Power Station in Monongalia County.
The proposed $2.48 billion gas plant will be built at the existing Fort Martin Power Station in Monongalia County. The solar projects will be located at Valley Point, near Albright; Davis, adjacent to the Town of Davis; and Wylie Ridge, in Weirton. The estimated cost of the solar projects is $182 million.
The companies also received approval for a surcharge to recover financing costs incurred during construction and after the facilities enter service, until those costs are included in base rates. The companies estimate the initial surcharge will increase residential customer bills by approximately $1.18 per month, or 0.9%.
The Commission directed the companies to provide updates on construction progress and costs as part of their annual filings in January 2027. The companies also must notify the commission at least 30 days before construction begins.
The companies initially filed their application in February, citing the need for additional electric generation capacity due to a projected shortage beginning in 2029 and continuing through 2045.
More information on this case can be found on the PSC website: www.psc.state.wv.us. Click on “Case Information” and access Case No. 26-0108-E-CN.
Add WVPB as a preferred source on Google to see more from our team