Federal, State Agencies Quiet About Mountain Valley Pipeline Failure

Groups that oppose the Mountain Valley Pipeline say last week’s failure in Roanoke County, Virginia, shows the risks the project poses to communities and property.

This story has been updated with comment from the Virginia Department of Environmental Quality.

The state and federal regulatory agencies that oversee the Mountain Valley Pipeline have said little about a rupture last week during a pressure test.

Groups that oppose the Mountain Valley Pipeline say last week’s failure in Roanoke County, Virginia, shows the risks the project poses to communities and property.

Because it is undergoing testing now, Wednesday’s rupture only released water. But the pipeline’s builder, Equitrans Midstream, has asked federal regulators for permission to begin operations at the end of this month.

West Virginia Public Broadcasting asked the company for comment and has yet to receive a reply. We also reached out to the principal state and federal agencies that oversee the project.

The Federal Energy Regulatory Commission and the Pipeline and Hazardous Materials Safety Administration have not replied.

After this story was first published, Irina Calos, a spokeswoman for the Virginia Department of Environmental Quality, said the breach occurred at 10 a.m. on May 1, during hydrostatic testing of the pipe.

“A section of pipe ruptured during this test, and municipal water used in the testing was discharged through the rupture,” she said.

Equitrans Midstream has removed the accumulated sediment, she said. She added that the incident would not affect any state permit approvals.

The public initially became aware of the incident because it was reported to a state database by a landowner.

Jessica Sims, Virginia field coordinator for Appalachian Voices, says her group has received very little information about the pipeline’s failure.

“Much more of a response would be helpful for community members to understand what happens now, what happens next,” she said, “What does this mean for the testing schedule? What does this mean for the overall integrity of the project?”

If FERC approves Equitrans Midstream’s application, 2 billion cubic feet of gas a day could be moving through the 303-mile pipeline next month from West Virginia into Virginia.

Had the rupture occurred then, the public would know much more about what happened and why. For example, the National Transportation Safety Board investigated a 2012 gas pipeline explosion in Sissonville, West Virginia, producing a detailed report.

But Sims says the state agency in Virginia doesn’t even publicly say when testing on the MVP will occur. She also says Freedom of Information Act requests to PHMSA, a small agency within the U.S. Department of Transportation, are taking months to complete.

She says state and federal regulators need to be more transparent.

“If there is a problem, how will the community know what has happened?” Sims asked. “And what is the plan in place to communicate that?”

Mountain Valley Pipeline Bursts During Pressure Testing In Virginia

A landowner observed sediment-laden water in her pasture on Wednesday morning and reported it to the Virginia Department of Environmental Quality.

A section of the Mountain Valley Pipeline ruptured during pressure testing Wednesday in Roanoke County, Virginia, according to a report from the state’s environmental agency.

A landowner observed sediment-laden water in her pasture on Wednesday morning and reported it to the Virginia Department of Environmental Quality.

The agency sent a construction compliance expert to investigate the origin of the water.

“The origin of the sediment-laden water reported in the complaint was from the rupture of a section of pipe during hydrostatic testing the morning of 5/1/2024,” wrote the expert, John McCutcheon.

The 300-mile MVP is undergoing pressure testing with water in anticipation of beginning operations later this month.

MVP’s builder, Equitrans Midstream, has asked the Federal Energy Regulatory Commission for permission to put the natural gas pipeline in service after May 23.

The company entered an agreement with the U.S. Pipeline and Hazardous Materials Safety Administration last year to ensure sections of pipe that had been exposed to the elements had not lost their corrosion-resistant coating.

Court challenges led to long pauses in construction until Congress last year required the project’s completion.

In its first quarter earnings report Tuesday, Equitrans Midstream said the project’s cost had increased to $7.85 billion, more than twice the original estimate.

McCutcheon’s report indicated that crews were preparing the site of the rupture for repairs.

Mountain Valley Pipeline Seeks Late May Approval To Start Operation

The company wrote that the 303-mile project will be mechanically complete by May 22 and seeks FERC’s approval by May 23.

The builders of the Mountain Valley Pipeline are seeking federal approval to begin operations within weeks.

MVP has sought approval from the Federal Energy Regulatory Commission to begin operations in late May.

The company wrote that the 303-mile project will be mechanically complete by May 22 and seeks FERC’s approval by May 23.

It says its customers with long-term contracts for natural gas from the pipeline become effective on June 1.

The $7.5 billion pipeline has been delayed and cost more than projected as environmental groups and landowners challenged the project in court.

The MVP is under a consent decree with the Pipeline and Hazardous Materials Safety Administration over a corrosion-resistant coating that may have degraded while large sections of pipe were exposed to weather during the delays.

That’s after groups challenged the safety of the exposed pipe. The company agreed to take corrective measures to eliminate any safety risk.

Various legal challenges to the pipeline’s construction ended last year when Congress passed, and President Joe Biden signed, a spending agreement that approved all remaining permits.

While some opponents continue to press forward, it appears they have few options remaining before the pipeline goes into service.

The MVP has a capacity of two billion cubic feet of gas a day. It will connect north-central West Virginia with southern Virginia and open up West Virginia gas production to new markets in the mid-Atlantic.

Company Seeks Cause of W.Va. Pipeline Explosion

  The operator of a pipeline that exploded in Brooke County is seeking the cause of the blast.

Monday’s explosion sent flames shooting several hundred feet into the air. No injuries were reported.

Enterprise Products operates the ATEX Express pipeline. Enterprise spokesman Rick Rainey tells The Intelligencer and Wheeling News-Register that the 20-inch diameter pipeline collects ethane from four natural gas processing plants in the area.

Rainey says Enterprise investigators are working with the federal Pipeline and Hazardous Materials Safety Administration to determine why the pipeline failed.

The federal agency is a division of the U.S. Department of Transportation. Transportation spokesman Damon Hill tells the newspaper that the agency has an inspector on-site.

Rainey says Enterprise is awaiting regulators’ approval to repair the pipeline.

W.Va. Gets Pipeline Safety Inspection Repayment

West Virginia’s pipeline safety program will receive nearly $453,000 from the federal government.

Congressman Nick Rahall announced the grant Monday from the U.S. Department of Transportation’s Pipeline and Hazardous Materials Safety Administration. More than $47 million is being distributed in 46 states, the District of Columbia and Puerto Rico.

The safety administration reimburses state pipeline safety programs for a portion of their total expenses in a given year. The state programs employ more than 320 inspectors who are responsible for 80 percent of the nation’s intrastate and distribution pipelines.

In West Virginia, the state Public Service Commission handles pipeline inspection and enforcement of safety regulations. 

Exit mobile version