Groups Challenge FERC Ruling On Mountain Valley Pipeline Extension

The legal challenge comes as another decision looms before FERC: whether to approve the 303-mile MVP to begin operating.

A group of environmental organizations is challenging a federal decision to give the Mountain Valley Pipeline three more years to build an extension from Virginia into North Carolina.

Appalachian Voices, the Center for Biological Diversity, the Natural Resources Defense Council and other groups petitioned the U.S. Court of Appeals in the District of Columbia Tuesday to review the Federal Energy Regulatory Commission’s decision to grant the MVP more time.

MVP’s builder, Equitrans Midstream, now has until June 2026 to complete the project, called MVP Southgate.

The legal challenge comes as another decision looms before the FERC: whether to approve the 303-mile MVP to begin operating.

Equitrans had requested an in-service date of May 23, but told the commission this week that it was completing construction and testing and wouldn’t be ready until the first week of June.

The environmental groups had asked FERC to reconsider its December decision granting the three year extension for MVP Southgate. FERC declined to do so last month.

Some of the same groups, and state and local officials, have asked FERC to deny MVP’s application to begin moving as much as 2 billion cubic feet of natural gas a day from West Virginia into Virginia.

On May 1, the pipe burst during a water pressure test in Bent Mountain, in Roanoke County, Virginia. Local residents say that part of the pipeline was installed in 2018.

On Wednesday, the Roanoke County Commission asked FERC to not permit MVP to begin operating until all safety testing is complete. The commission also asked that FERC and the Pipeline and Hazardous Materials Safety Administration share their findings on why the pipe failed the hydrostatic test.

MVP is projected to cost nearly $8 billion to complete, more than twice the original estimate.

Mountain Valley Pipeline’s Completion Delayed Again, Builder Says

In a letter to FERC Tuesday, the company said it expects the pipeline to be ready to operate in early June.

The Mountain Valley Pipeline won’t be ready to begin operations this week, the project’s builder told federal regulators.

Equitrans Midstream had asked the Federal Energy Regulatory Commission (FERC) to approve its application to enter service on Thursday. 

In a letter to FERC Tuesday, the company said it expects the pipeline to be ready to operate in early June.

Equitrans said it has to complete fewer than 10 welds and pressure test them with water. It said hydrostatic testing had been completed on 99 percent of the pipeline.

“Due to the extended construction duration to achieve weld-out, which has been associated with weather and environmental protection, Mountain Valley is adjusting its targeted in-service date to early June,” the company wrote to FERC.

Equitrans said it was not “premature,” as some critics had described, to approve the pipeline for service. 

The project has drawn heavy opposition since its beginning in 2018. The May 1 failure of a water pressure test at Bent Mountain, Virginia, amplified the concerns of those living near it.

State and federal regulators have been muted on how closely they’ve been looking at the rupture, which released an unknown volume of water and sediment onto adjacent land.

The company is under a consent agreement with the Pipeline and Hazardous Materials Safety Administration to correct any safety flaws in the pipeline.

Construction on the 303-mile, 42-inch natural gas line underwent long pauses as opponents challenged the project in federal court. A spending agreement Congress approved last summer granted all remaining permits the pipeline needed.

Residents of Bent Mountain say the section of pipe that failed, near the entrance to the Blue Ridge Parkway, was installed six years ago.

It is undergoing a metallurgical analysis, but regulators have not said whether they will publicly disclose the results of that examination.

The latest cost estimate to complete the MVP is nearly $8 billion, more than twice the original projection. The legal challenges, as well as the increased cost of construction and materials have driven up the cost.

When finished, the pipeline will move as much as 2 billion cubic feet a day of gas from north central West Virginia to southern Virginia. The company is planning an eventual extension into North Carolina to supply utility customers.

Safety Watchdog Has Its Eyes On The Mountain Valley Pipeline

Curtis Tate spoke with the organization’s executive director, Bill Caram, about its concerns with the project.

The Mountain Valley Pipeline (MVP) failed a water pressure test in Virginia earlier this month. The Pipeline Safety Trust urged federal regulators to take a close look at the failure. Curtis Tate spoke with the organization’s executive director, Bill Caram, about its concerns with the project.

This interview has been edited for length and clarity.

Tate: What are some possible causes of a pipeline failure during a water pressure test?

Caram: Unfortunately, we don’t know much about why the pipe failed the hydro test. There’s so many possible reasons for that failure, some of which would call into question the integrity of the entire pipeline and others could be very narrow and specific to one manufacturing defect on that one piece that once you replace it, you’re fine. So we really don’t know enough to know how concerned or not concerned the public should be about the integrity of the pipeline because of that hydro test failure. 

One of the big problems is there isn’t a lot of transparency and because of capacity limitations at the federal safety regulator (the Pipeline and Hazardous Materials Safety Administration, PHMSA), really a lot is left up to the operators to conduct all these inspections and tests, and then PHMSA comes in after the fact and basically checks their records on the tests and inspections that they did. Really a lot is left up to the operators and so there’s very little transparency involved, because it’s not the regulator’s doing these inspections in these tests.

Tate: A lot of groups, and state and local officials, have urged the Federal Energy Regulatory Commission (FERC) to deny the MVP’s in-service request. Why did your organization stop short of calling for that?

Caram: Again, because we don’t know enough about why the test failed, we came short of asking for FERC to deny the permit. What we really hope is that the federal regulators, the safety regulator, PHMSA and FERC, issuing the permit are fully informed of exactly what went wrong in that hydro test and that they have their hands in it, and that there are answers to that, before any permit is approved. Ideally, all of that would be made available to the public as well. That’s really what we want to see and what we want to know. I don’t think you can say, just because a pipeline failed a hydro test means it’s unfit for service. But it could, and so we would know exactly what went wrong and why and that there is an assurance to the public that the pipeline will be safe once it’s put into service. And that they’re transparent enough that the public really does feel really reassured, and I don’t think any of that is happening right now.

Tate: The Pipeline Safety Trust was founded after a fatal pipeline explosion. Can you tell us more about what you do?

Caram: We were founded after a pipeline tragedy here in Bellingham, Washington. In 1999, a hazardous liquid pipeline carrying gasoline ruptured and it spilled a quarter million gallons of gasoline into a creek that runs through the middle of town. It eventually ignited and it killed three boys, two 10-year-old boys and an 18-year-old. The families of those boys and the community, as they learned more and more about what went wrong in that pipeline tragedy, about the egregious actions, negligence from the operator and the complete lack of oversight from the federal government, they began calling for a national watchdog organization on the pipeline industry and its regulators. They lobbied to the Department of Justice to help found this organization and they were successful. 

When the settlement of the Olympic Pipeline Company happened, the criminal settlement, part of the money that they had to pay was set aside to form that watchdog organization and that’s what became the Pipeline Safety Trust. We work on a national level trying to bring accountability to both the pipeline industry and its regulators, both the federal and state regulators and to make pipelines safer to try to prevent any other community from having to go through the senseless grief from these preventable failures and tragedies that plagued Bellingham.

Tate: Is it appropriate for people who work for pipeline companies to be appointed to lead the agency that regulates them?

Caram: No industry polices itself well. It’s a hard balance to find where you want someone who is informed enough about the industry and the technical particulars to be an effective regulator. But you also don’t want someone who is part of that industry, because they don’t police themselves well, that can be a difficult balance to strike. I would rather err on the side of being an objective third party than having an industry insider. 

But I think the biggest problem with the federal regulations is really the amount of resources that are given from Congress. There is no way that they can be as effective of a regulator that we need in this country. Given the resources that they’re provided from Congress, they need a lot more. They also have a lot of restrictions put on them by Congress, where they’re adopting a new regulation. If it’s construction, or design standard, or things like that, it can’t apply to existing pipelines, it can only apply to new and replaced pipelines. They’re the only safety regulator in the country to have this in their defining statute. Where they cannot do a really extensive cost benefit analysis of any rule. And they have to justify any new rule by weighing how much it’s going to cost the industry versus what the benefits are. We’re talking about people’s lives. That really seems inappropriate to us as a safety watchdog.

Tate: What are your broader concerns about MVP?

Caram: We have a very large high pressure pipeline here when we’re talking about the Mountain Valley Pipeline. And through very steep terrain that has a history of land movement and landslides with pipe that was left out in the sun, damaging UV rays for far longer than the manufacturer’s recommendations. I don’t think we can be too careful. And I don’t think that the regulator and the operator can be too transparent. I think there’s a responsibility of the operator and the regulator to ensure that the community around this pipeline feel safe.

And I do want to commend PHMSA for issuing that safety order that became the consent agreement between Equitrans (the pipeline’s builder) and PHMSA that does take some extra steps. But the next step is assuring the public that, that consent agreement is on track and is being met as they as Equitrans seeks the permit to start the pipeline up.

Appeals Court Restores Jury Award In Mountain Valley Pipeline Case

The Fourth U.S. Circuit Court of Appeals in Richmond, Virginia, decided in favor of a family whose land was condemned to build the controversial 303-mile natural gas pipeline.

A federal appeals court has reinstated a larger jury verdict for some landowners affected by the Mountain Valley Pipeline.

The Fourth U.S. Circuit Court of Appeals in Richmond, Virginia, decided in favor of a family whose land was condemned to build the controversial 303-mile natural gas pipeline.

A jury awarded the Terry family of Roanoke County, Virginia, more than $500,000 for an eight-acre easement taken by the pipeline’s builder.

A U.S. district judge then reduced the award to $261,000.

In a decision published on Tuesday, a three-judge panel reversed the district court’s judgment.

The decision comes as Equitrans Midstream, the pipeline’s builder, is working furiously to complete the project and has requested federal permission to begin operating by June 1.

The pipeline failed a water pressure test near the Terry property in Roanoke County on May 1.

State and local officials and residents have asked the Federal Energy Regulatory Commission to deny the pipeline approval to begin operating.

Natalie Cox, a spokeswoman for Equitrans Midstream, said while the company believes the district judge was correct, “we look forward to concluding this outstanding issue and securing a final resolution in this matter.”

Watchdog: Feds Should Look At Mountain Valley Pipeline Rupture

A section of pipe burst during hydrostatic testing on May 1 at Bent Mountain, Virginia, releasing large volumes of municipal water and sediment into streams and on nearby properties.

A pipeline safety watchdog said federal regulators “should be on notice” about a pressure test failure on the Mountain Valley Pipeline earlier this month.

A section of pipe burst during hydrostatic testing on May 1 at Bent Mountain, Virginia, releasing large volumes of municipal water and sediment into streams and on nearby properties.

The incident was initially reported to the Virginia Department of Environmental Quality by a landowner. It took days for state and federal regulators, as well as the pipeline’s builder, to publicly address the incident.

The Pipeline Safety Trust, a nonprofit advocacy group, wrote to the Federal Energy Regulatory Commission on Friday requesting that the agency seek more information about the failed test.

Equitrans Midstream, the company building the 303-mile, 42-inch natural gas pipeline, has asked FERC for approval to begin operations by the end of the month.

The pipeline is intended to convey 2 billion cubic feet of gas a day from West Virginia to Virginia.

A group of 18 Virginia lawmakers asked FERC to deny the approval following the failed test.

The pipeline watchdog, while stopping short of calling for FERC to deny the approval, said the regulator should seek more information about the failure at Bent Mountain and others from the company and its federal regulator, the Pipeline and Hazardous Materials Safety Administration.

“Pipeline Safety Trust believes that FERC should be on notice about this failure, and that it should request more information from both MVP and PHMSA about this test and other hydrotests conducted on all segments of the pipe,” the letter said.

The pipeline builder has an agreement with PHMSA, part of the U.S. Department of Transportation, dating to October that requires it to fix any problems with sections of pipe that were exposed to weather and sunlight for prolonged periods.

The pipeline’s opponents, including environmental groups and landowners, have noted that exposure to the elements can degrade the pipe’s corrosion-resistant coating.

Landowners in the Bent Mountain area said the failed section of pipe was installed in 2018.

“It should also seek information about the remedial actions taken for this segment and whether MVP has taken care to ensure that similar weaknesses or abnormalities are addressed in a manner that meets PHMSA’s safety standards,” wrote the Pipeline Safety Trust’s Erin Sutherland, policy and program director/counsel, to FERC.

The Pipeline Safety Trust was founded after a fatal 1999 gasoline pipeline explosion in Bellingham, Washington. Its executive director, Bill Caram, testified to the House Transportation and Infrastructure Committee earlier this month as Congress considers a bill to reauthorize PHMSA.

In a letter to FERC also dated Friday, Equitrans Midstream’s Todd Normane, senior vice president and legal counsel, wrote the failed test demonstrated the safety practices the company is following.

“It is important for the public to know that Mountain Valley is committed to the safe and responsible construction and operation of the MVP project,” the letter said, “and hydrostatic testing is one component of a robust inspection and testing process designed to ensure system integrity.”

Residents Near Mountain Valley Pipeline Say Details Are Scarce

In spite of assurances from builders of the Mountain Valley Pipeline that it’s ready for service, some residents of a Virginia community want more answers.

In spite of assurances from builders of the Mountain Valley Pipeline that it’s ready for service, some residents of a Virginia community want more answers.

At Bent Mountain, Virginia, construction crews are working on the Mountain Valley Pipeline to begin operation in the next few weeks.

It’s been several days since a section of the pipe burst during testing, releasing water, not the large volume of natural gas it’s intended to carry.

Residents reported the sediment-laden water in creeks and on property on the morning of May 1 to the state’s Department of Environmental Quality.

It took nearly a week for the pipeline’s builder and state and federal agencies to respond to West Virginia Public Broadcasting’s questions about the pipeline failure. People who live near the pipeline have encountered similar frustrations.

Robin Austin, a Bent Mountain resident who’s been monitoring the nearly $8 billion project for a decade, says so many agencies are involved, it’s hard to know where to go for information.

“It’s really complicated,” she said. “You’ve got all these agencies. That’s a whole other problem. You don’t know who to send stuff to when you think something’s going on or you’d like information, so that makes it really challenging to get information.”

Austin says the pipeline’s builder, Equitrans Midstream, resumed hydrostatic testing – pressure testing with water – on Tuesday night, after repairing the damaged pipe.

The company says 269 miles of the 303-mile pipeline across two states – West Virginia and Virginia – have been successfully tested.

Equitrans has asked federal regulators for permission to begin operating the pipe by the end of the month. Landowners, including Austin, have doubts about whether it’s ready. 

“We want our community to be safe. If this has got to be here, it’s got to be safe,” Austin said. “That’s why we’ve observed for all these years. We’ll continue to do it. We’ll continue to do it if and when the gas is running through it.”

Tate reported from Bent Mountain, Virginia.

Exit mobile version