Asbestos Found in West Virginia University Arena

A West Virginia University official says test results at the WVU Coliseum confirm the presence of asbestos in materials that were exposed during recent construction activities.

WVU Environmental Health and Safety John Principe says the material discovered Friday was in an area above ceilings in restroom entrances that surround the concourse. He says the asbestos did not pose a health hazard and was only exposed by renovation work. He says the Coliseum was closed immediately after the asbestos was found.

WVU says the building will remain closed Monday as the collection of air samples continues. WVU says in a news release that a third party testing firm found air samples taken from the seating area and event level met regulatory standards for occupancy.

The 46-year-old Coliseum is undergoing a $15 million renovation. The building was closed in 1999 to 2000 while asbestos abatement was performed in exposed areas, including the 14,000-seat arena.

Lab Closed at WVU Hospitals Because of Asbestos Dust

A lab in West Virginia University Hospitals’ Health Sciences Building has temporarily closed following the discovery of asbestos in dust.

WVU Hospitals risk management and safety director Roger Osbourn tells The Dominion Post that the asbestos is an isolated incident. He says it most likely resulted when a pipe was bumped during renovations on the floor above the lab.

University environmental health and safety director John Principe says tests showed trace amounts of asbestos fibers. Air sample tests were negative.

Freedom Industries Plans Tank Demolition for Monday

  After running into asbestos problems, the company at the center of a January spill into West Virginia’s biggest water supply plans to start dismantling its tanks Monday.

Freedom Industries Chief Restructuring Officer Mark Welch described the new start time Tuesday in bankruptcy court in Charleston.

The company has delayed the teardown multiple times. Freedom stalled its start last weekend because of asbestos issues in tank gaskets and elsewhere.

Freedom is under state orders to demolish its Charleston site, where a leaky tank contaminated the water source downstream. For days, 300,000 residents couldn’t use tap water for most purposes.

Welch says the site should be cleared out in three or four weeks, but the company is proceeding slowly and carefully.

Freedom then must remediate the chemical damage done to the site.

Exit mobile version