Continue Reading Take Me to More NewsAppalachian Power’s Virginia customers will, after all, share in the cost of wastewater treatment projects at the John Amos and Mountaineer power plants.
The decision issued Tuesday by the Virginia State Corporation Commission is a reversal.
The projects will keep both plants operating past 2028. Appalachian Power had sought approval of the plan last year, but was rejected.
The company refiled the request with the commission earlier this year.
Last month, the commission’s senior hearing examiner recommended approval of the request, with the condition that Virginia ratepayers not share the cost of any uneconomic operation of the two plants.
The West Virginia Public Service Commission ordered Appalachian Power to operate the plants more, but tight coal supplies have limited how much they can run.
Virginia regulators approved a $21 million investment at Mountaineer and a $63.5 million investment in Amos, to be paid for by Appalachian Power’s Virginia customers.
The West Virginia PSC approved the investment at the two plants last year.